Customs & Project Logistics
Heavy-Lift Project Cargo Coordination
Client: Industrial equipment contractor
Route: Port Said → inland construction site

An industrial contractor needed oversized equipment cleared and delivered to a construction site to meet a fixed installation date tied to a broader project schedule.
We pre-filed customs documentation and secured oversize-load road permits before the vessel arrived, then coordinated port discharge directly onto specialized transport to skip a yard-storage delay.
Equipment reached the site two days ahead of the installation date, giving the contractor's crew buffer time instead of a schedule right up against the deadline.